Project Description:
ORANGE- BRIDGE REPLACEMENT, O-03-021, ROUTE 2 OVER ROUTE 202
This is the re-design of the former project #603590. Work will consist of replacing the bridge O-03-021 in the town of Orange.
Location:
  • Town of Orange
  • Construction Begins: Summer 2020
    Resident Engineer: Christopher Hoynoski
    Construction Bid Price: $15,170,052.00
    District: District 2

    Contracts (4) Progress
    # 110464 -- Construction Contract
    Bridge Replacement Br. No. O-03-021 (Steel) Route 2 (Mohawk Trail) over Route 202 (Daniel Shays Highway) Completed
    # 115791 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 07/15/2020
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY PERFORMANCE PROGRAM ON SYSTEM BRIDGE PROGRAM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/25/2010
    Project Initiation Form PIF Entered 10/25/2010
    Project Initiation Form PRC Submitted 10/25/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 12/21/2019
    Project Management
    100% Design 100% Package Received 10/25/2017
    25% Design 25% Package Received 12/04/2011
    25% Design 25% Package Received 03/20/2012
    25% Design 25% Package Received 03/20/2012
    25% Design 25% Package Received 04/29/2015
    25% Design 25% Package Comments to DE 08/31/2015
    75% Design 75% Package Received 04/03/2017
    75% Design 75% Package Comments to DE 08/04/2017
    Final Design PS&E Received 05/22/2018
    Final Design PS&E to FAPRO 12/09/2019
    Consultant Contract Process NTP Issued 10/11/2010