Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BROOKLINE- PEDESTRIAN BRIDGE REHABILITATION, B-27-016, OVER MBTA OFF CARLTON STREET
This project involves the rehabilitation of a historic steel truss pedestrian bridge built in 1894. Due to the poor condition it is currently closed to pedestrian traffic since 1976. This project will restore this bridge as a pedestrian connection.
Location:
  • Town of Brookline
  • Construction Begins: Autumn 2020
    Resident Engineer: Charles Labbee
    Construction Bid Price: $3,955,053.50
    District: District 6

    Contracts (1) Progress
    # 112791 -- Construction Contract
    Pedestrian Bridge Repairs and Related Work (Including Painting) Br. No. B-27-016 Carlton Street Footbridge over the MBTA D Green Line (Re-Advertised Project) 100% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 12/09/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/26/2010
    Project Initiation Form PIF Entered 10/29/2010
    Project Initiation Form PRC Submitted 11/01/2010
    Project Review Committee PRC Approved 08/12/2010
    Project Review Committee Letter 11/12/2010
    Project Status Advertised 09/07/2019
    Project Status Advertised 09/05/2020
    Project Management
    100% Design 100% Package Received 05/11/2018
    100% Design 100% Package Comments to DE 07/19/2018
    25% Design 25% Package Received 09/21/2011
    25% Design 25% Package Received 06/20/2014
    25% Design 25% Package Comments to DE 11/22/2011
    25% Design 25% Package Comments to DE 03/03/2015
    25% Design 25% Package Received - Resub 5 02/17/2017
    25% Design Design Public Hearing 11/04/2015
    75% Design 75% Package Received 06/08/2016
    75% Design 75% Package Comments to DE 08/30/2016
    Final Design PS&E Received 07/16/2019
    Final Design PS&E to FAPRO 08/19/2019
    Final Design PS&E Received - Resub 1 08/17/2020