BOSTON- INTERSECTION IMPROVEMENTS @ GALLIVAN BOULEVARD (ROUTE 203) & MORTON STREET
Project will propose traffic signal improvements and upgrades as well as possible lane configuration changes to better manage traffic at this intersection formerly under DCR jurisdiction.
Location:
  • City of Boston
  • Construction Begins: Winter 2018/2019
    Resident Engineer: Carmine LaVita
    Construction Bid Price: $3,197,373.27
    District: District 6

    Contracts (6) Progress
    # 106136 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Gallivan Boulevard (Route 203) and Morton Street Completed
    # 54826 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 57734 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69763 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77885 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/07/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/29/2010
    Project Initiation Form PIF Entered 11/01/2010
    Project Initiation Form PRC Submitted 11/09/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 10/06/2018
    Project Management
    100% Design 100% Package Received 12/12/2016
    100% Design 100% Package Comments to DE 02/03/2017
    25% Design 25% Package Received 10/08/2013
    25% Design 25% Package Received 02/02/2016
    25% Design 25% Package Comments to DE 12/02/2014
    25% Design 25% Package Comments to DE 05/04/2016
    25% Design Design Public Hearing 12/18/2014
    25% Design Design Public Hearing 03/19/2015
    25% Design Design Public Hearing 04/01/2015
    25% Design Design Public Hearing 01/19/2017
    75% Design 75% Package Received 12/12/2016
    75% Design 75% Package Comments to DE 02/03/2017
    Final Design PS&E Received 08/14/2017
    Final Design PS&E to Peer Reviewer 08/14/2017
    Final Design PS&E Received - Resub 1 09/26/2018