Project Description:
DISTRICT 3- SCHEDULED & EMERGENCY BRIDGE SUBSTRUCTURE REPAIRS AT VARIOUS LOCATIONS
Various levels of deterioration to the abutments, columns, caps, etc. exist at a number of bridges throughout the District. This contract will enable the District to address emergency problems as well as schedule and perform needed improvements and repairs on site assessments. If these repairs are not performed in a timely manner, further deterioration will occur - requiring more costly repairs in the future.
Location:
Resident Engineer: Jacqueline Ventriglia
Construction Contract Value: $2,863,083.18
Construction Bid Price: $1,752,345.00
Initial Construction Estimate: $1,925,550.00
District: District 3

Contracts (1) Progress
# 69095 -- Construction Contract
Scheduled and Emergency Bridge Substructure Repairs at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/12/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/02/2010
    Project Initiation Form PIF Entered 11/02/2010
    Project Initiation Form PRC Submitted 11/03/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 12/01/2010
    Project Status Advertised 05/21/2011
    Project Management
    100% Design 100% Package Received 05/12/2011
    100% Design 100% Plans Approved 05/05/2011
    100% Design 100% Plans Complete 05/10/2011
    Final Design PS&E Received 05/12/2011
    Final Design PS&E to FAPRO 05/12/2011