| Project Description: |
DISTRICT 3- SCHEDULED & EMERGENCY BRIDGE DECKS REPAIRS AT VARIOUS LOCATIONS
Various levels of bridge deck deterioration exist at a number of bridges throughout the District. This contract will enable the District to address emergency problems as well as schedule and perform needed improvements and repairs on site assessments. If these repairs are not performed in a timely manner, further deterioration will occur - requiring more costly repairs in the future.
|
| Location: | |
| Resident Engineer: | Paul Tivnan![]() |
| Construction Contract Value: | $2,473,255.00 |
| Construction Bid Price: | $1,264,355.00 |
| Initial Construction Estimate: | $1,843,785.00 |
| District: | District 3 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||