STURBRIDGE- RESURFACING AND RELATED WORK ON ROUTE 20, FROM ROUTE 49 TO I-84
The project involves resurfacing Route 20, from Route 49 to I-84, a distance of 2.0 miles. Additional work includes adjusting drainage structures, resetting curbing and edging, installtion of signs and pavement markings.
Location:
  • Town of Sturbridge
  • Resident Engineer: Stanley Choinski
    Construction Bid Price: $2,434,773.54
    District: District 3

    Contracts (1) Progress
    # 90472 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 20 (Charlton Road) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/16/2016
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/12/2010
    Project Initiation Form PIF Entered 11/12/2010
    Project Initiation Form PRC Submitted 11/12/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 09/05/2015
    Project Management
    100% Design 100% Package Received 04/29/2015
    25% Design 25% Package Received 01/09/2015
    75% Design 75% Package Received 01/09/2015
    75% Design 75% Package Comments to DE 02/12/2015
    75% Design 75% Package Comments to DE 02/20/2015
    75% Design 75% Plans Approved 01/22/2015
    Final Design PS&E Received 04/29/2015
    Final Design PS&E to FAPRO 09/01/2015