BEDFORD- BILLERICA- CHELMSFORD- CABLE BARRIER INSTALLATION ON ROUTE 3
A Road Side Safety Audit (RSA) has identified this location as a high risk for median cross-over accidents. The study section (approx. 8.5 miles) identified 6.1 miles of open median. Cable barrier is recommended and will be installed between Exits 26 and 29.
|
| Location: |
|
| Resident Engineer: | Stephen Doherty![]() |
| Construction Contract Value: | $1,096,021.00 |
| Construction Bid Price: | $922,564.65 |
| Initial Construction Estimate: | $1,000,625.00 |
| District: | District 4 |
|