BEDFORD- BILLERICA- CHELMSFORD- CABLE BARRIER INSTALLATION ON ROUTE 3
A Road Side Safety Audit (RSA) has identified this location as a high risk for median cross-over accidents. The study section (approx. 8.5 miles) identified 6.1 miles of open median. Cable barrier is recommended and will be installed between Exits 26 and 29.
Location:
  • Town of Bedford
  • Town of Billerica
  • Town of Chelmsford
  • Resident Engineer: Stephen Doherty
    Construction Contract Value: $1,096,021.00
    Construction Bid Price: $922,564.65
    Initial Construction Estimate: $1,000,625.00
    District: District 4

    Contracts (1) Progress
    # 75708 -- Construction Contract
    Median Cable Barrier Installation along a Section of Route 3. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/25/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/15/2010
    Project Initiation Form PIF Entered 11/15/2010
    Project Initiation Form PRC Submitted 11/15/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/23/2010
    Project Status Advertised 09/22/2012
    Project Management
    25% Design 25% Package Received 02/08/2011
    75% Design 75% Package Received 02/18/2011
    75% Design 75% Package Comments to DE 04/14/2011
    Final Design PS&E Received 10/06/2011
    Final Design PS&E to FAPRO 09/11/2012