Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY FACILITIES REPAIR AND IMPROVEMENT AT VARIOUS LOCATIONS
This project calls for the repair and improvement of facilites at a number of locations throughout District 6, this will include both both scheduled and emergency repairs.
Location:
Resident Engineer: John Catalogna
Construction Contract Value: $494,842.50
Construction Bid Price: $224,785.50
Initial Construction Estimate: $229,925.00
District: District 6

Contracts (1) Progress
# 68904 -- Construction Contract
Scheduled and Emergency Facilities Repairs and Improvement at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/20/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2010
    Project Initiation Form PIF Entered 11/17/2010
    Project Initiation Form PRC Submitted 11/17/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 05/07/2011
    Project Management
    100% Design 100% Package Received 01/19/2011
    Final Design PS&E Received 04/15/2011
    Final Design PS&E to FAPRO 05/03/2011