Project Description:
DISTRICT 6- HIGHWAY LIGHTING REPLACEMENT OR REPAIRS AT VARIOUS LOCATIONS
Project involves scheduled and emergency repairs and or replacements of lighting facilities at a number of locations througout District 6.
Location:
  • City of Boston
  • Resident Engineer: Daniel Mullaly
    Construction Contract Value: $1,392,284.00
    Construction Bid Price: $869,784.00
    Initial Construction Estimate: $925,799.00
    District: District 6

    Contracts (1) Progress
    # 68374 -- Construction Contract
    Roadway Lighting Repairs at Various Locations. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/19/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2010
    Project Initiation Form PIF Entered 11/17/2010
    Project Initiation Form PRC Submitted 11/17/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 03/19/2011
    Project Status Advertised 04/16/2011
    Project Management
    Final Design PS&E Received 02/04/2011
    Final Design PS&E to FAPRO 03/04/2011