Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY DRAWBRIDGE MAINTENANCE, REPAIRS, AND OPERATION AT VARIOUS LOCATIONS
Project involves the maintenance, repairs, and operations of drawbridges through out D-6.
Location:
Resident Engineer: Mario Ferragamo
Construction Contract Value: $2,770,260.00
Construction Bid Price: $1,391,260.00
Initial Construction Estimate: $2,082,575.00
District: District 6

Contracts (1) Progress
# 73928 -- Construction Contract
Scheduled and Emergency Drawbridge Operation, Repairs and Maintenance at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/09/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2010
    Project Initiation Form PIF Entered 11/17/2010
    Project Initiation Form PRC Submitted 11/17/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 05/26/2012
    Project Management
    100% Design 100% Package Received 05/22/2012
    25% Design 25% Package Received 01/18/2012
    75% Design 75% Package Received 03/02/2012
    Final Design PS&E Received 05/22/2012
    Final Design PS&E to FAPRO 05/23/2012