Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 6- SCHEDULED AND EMERGENCY CLEANING OF DRAINAGE STRUCTURES
Project involves the scheduled and emergency cleaning of drainage structures at various locations through out D-6.
Location:
  • City of Boston
  • Resident Engineer: David Durkee
    Construction Contract Value: $476,133.94
    Construction Bid Price: $399,783.94
    Initial Construction Estimate: $463,030.00
    District: District 6

    Contracts (1) Progress
    # 70216 -- Construction Contract
    Scheduled and Emergency Drainage Structure Cleaning at Various Locations. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/20/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Maintenance
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2010
    Project Initiation Form PIF Entered 11/17/2010
    Project Initiation Form PRC Submitted 11/17/2010
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 07/30/2011
    Project Management
    100% Design 100% Package Received 06/14/2011
    Final Design PS&E Received 06/14/2011
    Final Design PS&E to FAPRO 07/18/2011