Project Description:
DISTRICT 6- INSTALLATION & REFURBISHMENT OF CRASH CUSHION SYSTEMS AT VARIOUS LOCATIONS
Project involves the installation or refurbishment of crash cushion systems at various location through out D-6.
Location:
Resident Engineer: Michael McGonagle
Construction Contract Value: $842,588.67
Construction Bid Price: $363,235.00
Initial Construction Estimate: $385,009.00
District: District 6

Contracts (1) Progress
# 83800 -- Construction Contract
Scheduled and Emergency Repairs and Replacement of Impact Attenuators at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/20/2015
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/17/2010
    Project Initiation Form PIF Entered 11/17/2010
    Project Initiation Form PRC Submitted 11/18/2010
    Project Review Committee PRC Approved 11/18/2010
    Project Review Committee Letter 11/24/2010
    Project Status Advertised 07/26/2014
    Project Management
    Final Design PS&E Received 07/11/2014
    Final Design PS&E Received 02/04/2015