WAREHAM- BRIDGE REPLACEMENT, W-06-002, PAPER MILL ROAD OVER WEWEANTIC RIVER
The work on this project will consist of the full replacement of Paper Mill Road over the Weweantic River in the Town of Wareham. This will include replacement of the existing structure with an anticipated detour for full closure of the bridge. The proposed bridge will consist of a precast concrete arch, a new wearing surface, painted steel bridge rail, and limited approach roadway work.
Location:
  • Town of Wareham
  • Construction Begins: Autumn 2016
    Resident Engineer: Matthew Lambert
    Construction Bid Price: $1,698,698.30
    District: District 5

    Contracts (2) Progress
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 94337 -- Construction Contract
    Bridge Replacement Br. No. W-06-002 (Concrete) Paper Mill Road over Weweantic River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 09/28/2016
    Contract Information
    Project Designer:
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/19/2010
    Project Initiation Form PIF Entered 02/01/2011
    Project Initiation Form PRC Submitted 02/01/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 05/14/2016
    Project Management
    100% Design 100% Package Received 12/23/2015
    100% Design 100% Package Comments to DE 01/28/2016
    25% Design 25% Package Received 03/25/2015
    25% Design 25% Package Comments to DE 04/27/2015
    25% Design 25% Package Comments to DE 06/16/2015
    25% Design Design Public Hearing 06/23/2015
    75% Design 75% Package Received 08/17/2015
    75% Design 75% Package Comments to DE 09/11/2015
    Final Design PS&E Received 03/16/2016
    Final Design PS&E to FAPRO 05/10/2016