NORTHAMPTON- PARK & RIDE CONSTRUCTION AT THE VA MEDICAL CENTER
The project consists of expanding / reconstructing an existing Veteran's Administration Medical Center parking lot to accommodate park & ride use. Also included will be signal upgrades at the VAMC entrance drive on Route 9, signage, and upgrades to the existing parking lot lighting. The lot will provide approximately 75 parking spaces (50 for park & ride users, 25 for the current VA users) along with a bicycle rack, pedestrian walks, a pedestrian connection to the Look Park Rail Trail and a bus stop with shelter.
Location:
  • City of Northampton
  • Resident Engineer: Joseph McCarthy
    Construction Contract Value: $842,186.00
    Construction Bid Price: $757,069.40
    Initial Construction Estimate: $833,370.00
    District: District 2

    Contracts (4) Progress
    # 62609 -- Construction Contract
    Park and Ride Construction (Including Traffic Signals) at the VA Medical Center. Completed
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/20/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/26/2010
    Project Initiation Form PIF Entered 11/26/2010
    Project Initiation Form PRC Submitted 11/26/2010
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 01/26/2013
    Project Management
    100% Design 100% Package Received 10/10/2012
    100% Design 100% Package Comments to DE 11/13/2012
    25% Design 25% Package Received 04/17/2012
    25% Design 25% Package Comments to DE 06/04/2012
    25% Design Design Public Hearing 07/24/2012
    75% Design 75% Package Received 10/10/2012
    75% Design 75% Package Comments to DE 11/13/2012
    Final Design PS&E Received 12/17/2012
    Final Design PS&E to FAPRO 01/23/2013
    Consultant Contract Process Scope to DE 10/03/2011
    Consultant Contract Process NTP Issued 02/06/2012
    Consultant Contract Process Workhours Approved 01/11/2012