| Project Description: |
BOSTON- DECK REPLACEMENT, B-16-056, CAMBRIDGE STREET OVER I-90, INCLUDES PRESERVATION OF B-16-057, LINCOLN STREET PED OVERPASS OVER I-90
Work consists of deck replacement of Cambridge Street over I-90 as well as preservation of Lincoln Street Pedestrian Overpass over I-90.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Spring 2014 |
| Project Manager: | John Fallon![]() |
| Estimated Total Contract Cost: | $11,053,614.70 |
| Estimated Total Federal Participating Construction Cost: | $11,530,333.55 |
| District: | District 6 |
| Current Status: | This project has been advertised for construction bids. (as of 02/08/2014 ) |
|
Bridges
|
||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||