Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- DECK REPLACEMENT, B-16-056, CAMBRIDGE STREET OVER I-90, INCLUDES PRESERVATION OF B-16-057, LINCOLN STREET PED OVERPASS OVER I-90
Work consists of deck replacement of Cambridge Street over I-90 as well as preservation of Lincoln Street Pedestrian Overpass over I-90.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2014
    Project Manager: John Fallon
    Estimated Total Contract Cost: $11,053,614.70
    Estimated Total Federal Participating Construction Cost: $11,530,333.55
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 02/08/2014 )

    Contracts (4) Progress
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 12/06/2010
    Project Initiation Form PIF Entered 01/21/2011
    Project Initiation Form PRC Submitted 01/21/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 02/08/2014
    Project Management
    100% Design 100% Package Received 05/18/2012
    100% Design 100% Package Comments to DE 07/27/2012
    25% Design Design Public Hearing 06/18/2013
    Final Design PS&E Received 02/03/2014
    Final Design PS&E Received 04/22/2014
    Final Design PS&E to FAPRO 02/04/2014
    Final Design PS&E to FAPRO 04/22/2014