Project Description: |
FALL RIVER- SUPERSTRUCTURE REPLACEMENT, F-02-052, HERMAN STREET OVER ROUTE 79
The purpose of this project is to replace the superstructure of the bridge carrying Herman Street over SR 79 with a two span steel stringer, and concrete deck structure. Precast bridge units are anticipated in order to facilitate construction.
|
Location: |
|
Resident Engineer: | Marc Cardinal |
Construction Contract Value: | $2,718,096.00 |
Construction Bid Price: | $2,464,784.80 |
Initial Construction Estimate: | $3,256,424.25 |
District: | District 5 |
|
Bridges
|
|
|
|
|