FALL RIVER- SUPERSTRUCTURE REPLACEMENT, F-02-052, HERMAN STREET OVER ROUTE 79
The purpose of this project is to replace the superstructure of the bridge carrying Herman Street over SR 79 with a two span steel stringer, and concrete deck structure. Precast bridge units are anticipated in order to facilitate construction.
Location:
  • City of Fall River
  • Resident Engineer: Marc Cardinal
    Construction Contract Value: $2,718,096.00
    Construction Bid Price: $2,464,784.80
    Initial Construction Estimate: $3,256,424.25
    District: District 5

    Contracts (5) Progress
    # 55039 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 60139 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77861 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79734 -- Construction Contract
    Bridge Superstructure Replacement (F-02-052) (Prefabricated Bridge Units) - Herman Street over Route 79. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/30/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/10/2011
    Project Initiation Form PIF Entered 01/10/2011
    Project Initiation Form PRC Submitted 01/18/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 09/14/2013
    Project Management
    25% Design 25% Package Received 01/17/2013
    25% Design 25% Package Comments to DE 03/04/2013
    75% Design 75% Package Received 05/29/2013
    75% Design 75% Package Comments to DE 07/17/2013
    Final Design PS&E Received 08/16/2013
    Final Design PS&E to FAPRO 09/11/2013