BARNSTABLE- INTERSECTION IMPROVEMENTS AT FALMOUTH ROAD (ROUTE 28) AND BEARSES WAY
Work on this project consists of new traffic signal systems at the Route 28/Bearses Way intersection and Route 28/Cape Cod Mall entrance intersection as well as corridor improvements between. The project will incorporate a 4 lane cross section with a raised median on Rte 28, the installation of shared use paths, sidewalks and bike lanes at the intersections and on Rte 28 between the intersections. Geometric improvements are proposed at the Rte 28/Bearses Way intersection and Rte 28/Cape Cod Mall intersection to improve safety and traffic flow.
Location:
  • Town of Barnstable
  • Resident Engineer: Michael King
    Construction Bid Price: $6,522,364.47
    District: District 5

    Contracts (4) Progress
    # 57791 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to the MassHighway on an open end basis located in the Cape Cod Commission region. Final
    # 69762 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90729 -- Construction Contract
    Roadway Reconstruction (Including Signals and Retaining Walls) at the Intersection of Route 28 (Falmouth Road) and Bearses Way. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/21/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/20/2011
    Project Initiation Form PIF Entered 01/20/2011
    Project Initiation Form PRC Submitted 01/20/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 06/22/2015
    100% Design 100% Package Comments to DE 08/10/2015
    25% Design 25% Package Received 06/28/2013
    25% Design 25% Package Comments to DE 12/30/2013
    25% Design Design Public Hearing 12/22/2014
    75% Design 75% Package Received 02/20/2015
    75% Design 75% Package Comments to DE 04/23/2015
    Final Design PS&E Received 08/20/2015
    Final Design PS&E Received 09/08/2015
    Final Design PS&E Received 09/24/2015
    Final Design PS&E to FAPRO 09/15/2015
    Consultant Contract Process Scope to DE 01/07/2011
    Consultant Contract Process NTP Issued 04/25/2011
    Consultant Contract Process Workhours Approved 04/21/2011