Project Description:
ADAMS- NORTH ADAMS- BRIDGE DECK REPAIRS & RELATED WORK, A-04-001, ROUTE 8 (PARK STREET) OVER THE ASHWILLTICOOK RIVER TRAIL & N-14-016, EASTERN SPAN ROUTE 2 (VETERANS MEMORIAL DRIVE) OVER HOOSIC RIVER
Various levels of bridge deck deterioration exist at a number of bridges throughout the District. This contract will enable the District to address emergency problems as well as schedule and perform needed improvements and repairs on site assessments. If these repairs are not performed in a timely manner, further deterioration will occur - requiring more costly repairs in the future.
Location:
  • Town of Adams
  • City of North Adams
  • Resident Engineer: Daniel Evans
    Construction Contract Value: $906,479.96
    Construction Bid Price: $587,723.80
    Initial Construction Estimate: $603,244.00
    District: District 1

    Contracts (1) Progress
    # 75704 -- Construction Contract
    Bridge Deck Repairs and Related Work at Various Locations Including (Br. A-04-001) - Route 8 (Park Street) over the Ashwillticook Rail Trail & (Br. N-14-016) - Eastern Span Ro Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/11/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/24/2011
    Project Initiation Form PIF Entered 01/24/2011
    Project Initiation Form PRC Submitted 01/25/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 09/22/2012
    Project Management
    Final Design PS&E Received 01/05/2012
    Final Design PS&E to FAPRO 09/05/2012