Project Description:
HINSDALE- PERU- RECONSTRUCTION OF SKYLINE TRAIL (MIDDLEFIELD ROAD)
This 2 mile long project begins at the intersection of Route 8 in Hinsdale and ends approximately 300 ft east of the Hinsdale/Peru town line. The current proposal is to rehabilitate the roadway by reclamation; placing a new bituminous surface over the reclaimed base. Two to three feet of widening is proposed to meet low speed, low volume road standards and to achieve consistent roadway width. Some minor geometric improvements at intersections are also proposed. The existing “open” drainage system will be rehabilitated; maintaining existing discharge locations, and adding inlet structures where needed. A 5-ft by 7-ft concrete box culvert will be rehabilitated, and stone aprons will be placed at various outlets to prevent erosion. Unpaved shoulders will be re-graded and protected with dense graded crushed stone. Other disturbed areas will receive loam and seed. Existing guardrail will be replaced or upgraded as needed. New guardrail will be installed at select locations as warranted. New traffic signs and pavement markings will also be included in the project.
Location:
  • Town of Hinsdale
  • Town of Peru
  • Construction Begins: Autumn 2021
    Resident Engineer: Michael Cullett
    Construction Bid Price: $5,826,927.00
    District: District 1

    Contracts (2) Progress
    # 115501 -- Construction Contract
    Roadway Reconstruction and Related Work (Including 3 Bridges and 2 Culverts) along a Section of Middlefield Road (Skyline Trail) Completed
    # 65756 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final

    Bridges

    Contract Dates
    Notice to Proceed: 10/14/2021
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/26/2011
    Project Initiation Form PIF Entered 01/26/2011
    Project Initiation Form PRC Submitted 02/03/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 07/24/2021
    Project Management
    100% Design 100% Package Received 09/02/2020
    25% Design 25% Package Received 02/28/2019
    25% Design 25% Package Comments to DE 05/01/2019
    25% Design Design Public Hearing 06/26/2019
    75% Design 75% Package Received 01/31/2020
    75% Design 75% Package Comments to DE 04/06/2020
    Final Design PS&E Received 12/01/2020
    Final Design PS&E Received - Resub 1 04/21/2021
    Final Design PS&E Received - Resub 2 06/15/2021