Project Description:
ATHOL- RECONSTRUCTION OF WEST ROYALSTON ROAD, FROM SILVER LAKE STREET TO THE ROYALSTON T.L. (APPROX. 2 MILES)
Project consists of reclaiming, box-widening and paving West Royalson Road. Drainage system improvements as well as new signs and pavement markings will be included.
Location:
  • Town of Athol
  • Resident Engineer: Matthew Minihan
    Construction Contract Value: $1,996,354.00
    Construction Bid Price: $1,776,826.70
    Initial Construction Estimate: $1,807,288.00
    District: District 2

    Contracts (1) Progress
    # 80795 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Route 32 (West Royalston Road) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/30/2014
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/26/2011
    Project Initiation Form PIF Entered 01/26/2011
    Project Initiation Form PRC Submitted 01/26/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 12/21/2013
    Project Management
    100% Design 100% Package Received 09/12/2013
    100% Design 100% Package Comments to DE 10/08/2013
    25% Design 25% Package Received 02/16/2012
    25% Design 25% Package Received 07/06/2012
    25% Design 25% Package Comments to DE 04/17/2012
    25% Design Design Public Hearing 10/24/2012
    75% Design 75% Package Received 05/30/2013
    75% Design 75% Package Comments to DE 06/21/2013
    Final Design PS&E Received 11/21/2013
    Final Design PS&E to FAPRO 12/18/2013
    Consultant Contract Process NTP Issued 06/23/2011