Project Description:
ASHFIELD- RETAINING WALL REPAIRS ON ROUTE 116 ALONG THE SOUTH RIVER (2 LOCATIONS)
The two existing retaining walls, located along Route 116 (eastbound) and South River, in the vicinity of the Bullitt Road intersection in Ashfield, will be replaced. The new retaining walls will be constructed behind the existing walls (farther away from the river) which would reduce potential work in the river. The eastern wall will be constructed from the Bullitt Road intersection to approximately 800 feet east of it. The western wall will extend from approximately 800 to 1,700 feet west of the intersection. The project also includes limited widening of Route 116 (along the wall alignments) and construction of a new stone retaining wall along Route 116 westbound (and in the eastern wall construction area), where cuts into the hillside will be needed.
Location:
  • Town of Ashfield
  • Resident Engineer: Michael Dostal
    Construction Contract Value: $1,855,133.00
    Construction Bid Price: $1,677,621.00
    Initial Construction Estimate: $2,509,286.00
    District: District 1

    Contracts (2) Progress
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 72304 -- Construction Contract
    Retaining Wall Repairs at 2 Locations along Route 116 (Conway Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/29/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Section 115
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/28/2011
    Project Initiation Form PIF Entered 01/28/2011
    Project Initiation Form PRC Submitted 01/31/2011
    Project Review Committee PRC Approved 02/10/2011
    Project Status Advertised 12/31/2011
    Project Management
    100% Design 100% Package Received 05/26/2011
    100% Design 100% Package Comments to DE 06/21/2011
    100% Design 100% Plans Approved 06/21/2011
    25% Design 25% Package Received 01/19/2011
    25% Design 25% Package Comments to DE 02/18/2011
    25% Design 25% Package Approved 02/18/2011
    25% Design Design Public Hearing 03/29/2011
    75% Design 75% Package Received 03/15/2011
    75% Design 75% Plans Approved 04/08/2011
    Final Design PS&E Received 08/02/2011
    Final Design PS&E Received 11/04/2011
    Final Design PS&E Received 11/07/2011
    Final Design PS&E Received 11/21/2011
    Final Design PS&E Received 12/28/2011
    Final Design PS&E to FAPRO 12/28/2011
    Consultant Contract Process NTP Issued 07/13/2010
    Consultant Contract Process Workhours Approved 07/13/2010