WESTON- MILLING & PAVING ON I-90 (MILE MARKER 121.1 TO 123.2 INCLUDING INT 14 & 15)
Project involves the milling 2 inches and resurfacing the road. The limits of the project, along a section of I-90, will be between mile marker 121.1 and 123.2. This limt includes two interchanges: 14 and 15. The project will likely be funded with Western Turnpike Toll capital funds.
|
Location: |
|
Resident Engineer: | Peter Tramontozzi |
Construction Contract Value: | $5,232,530.00 |
Construction Bid Price: | $4,419,148.78 |
Initial Construction Estimate: | $3,684,000.00 |
District: | District 6 |
|