Project Description:
NANTUCKET- MULTI-USE PATH CONSTRUCTION, FROM WASHINGTON STREET TO ORANGE STREET
Work on this project consists of constructing a shared use path from Washington Street to Orange Street, primarily along the abandoned railroad bed. Work on the connecting streets is proposed to improve accommodation for non-motorized use.
Location:
  • Town of Nantucket
  • Construction Begins: Autumn 2016
    Resident Engineer: Malcolm Lavalley
    Construction Bid Price: $2,440,770.00
    District: District 5

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 93543 -- Construction Contract
    Multi-Use Trail Reconstruction and Related Work (Including Steel Sheeting Retaining Wall) along a Section of Goose Pond Lane and Orange Street. (Re-Advertised Project) 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/31/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/14/2011
    Project Initiation Form PIF Entered 04/12/2011
    Project Initiation Form PRC Submitted 04/12/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 09/12/2015
    Project Status Advertised 03/05/2016
    Project Management
    100% Design 100% Package Received 01/31/2014
    100% Design 100% Package Comments to DE 04/07/2014
    25% Design 25% Package Received 01/04/2012
    25% Design 25% Package Received 03/15/2013
    25% Design 25% Package Comments to DE 10/22/2012
    25% Design 25% Package Comments to DE 06/10/2013
    25% Design Design Public Hearing 09/26/2013
    75% Design 75% Package Received 01/31/2014
    75% Design 75% Package Comments to DE 04/07/2014
    Final Design PS&E Received 06/25/2015
    Final Design PS&E Received 01/20/2016
    Final Design PS&E to FAPRO 09/08/2015
    Final Design PS&E to FAPRO 02/22/2016
    Final Design PS&E to FAPRO 05/02/2016