Project Description:
WORCESTER- MAIN STREET BUSINESS DISTRICT STREETSCAPE IMPROVEMENTS
The scope of work involves resurfacing, sidewalk reconstruction and streetscape elements, including trash receptacles, benches and bike racks, on five downtown area roadways – Main Street, Southbridge Street, Foster Street, Front Street and Franklin Street. These are all roadways abutting or in close proximity to their City Hall and City Common.
Location:
  • City of Worcester
  • Construction Begins: Spring 2018
    Resident Engineer: Webster Larkin Sr
    Construction Bid Price: $7,989,695.25
    District: District 3

    Contracts (1) Progress
    # 102068 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) in the Central Business District along a Section of Main Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/02/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/18/2011
    Project Initiation Form PIF Entered 03/18/2011
    Project Initiation Form PRC Submitted 04/25/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/25/2011
    Project Status Advertised 08/26/2017
    Project Management
    100% Design 100% Package Received 05/30/2017
    100% Design 100% Package Comments to DE 07/07/2017
    25% Design 25% Package Received 07/23/2013
    25% Design 25% Package Received 05/18/2015
    25% Design 25% Package Comments to DE 01/28/2014
    25% Design Design Public Hearing 12/09/2015
    75% Design 75% Package Received 11/28/2016
    75% Design 75% Package Comments to DE 01/05/2017
    Final Design PS&E Received 08/02/2017
    Final Design PS&E to Peer Reviewer 08/07/2017
    Final Design Peer Review Comments to DE 08/21/2017
    Final Design PS&E to FAPRO 08/14/2017