Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HUBBARDSTON- RESURFACING AND RELATED WORK ON ROUTE 68, FROM BRIGHAM ROAD TO THE RUTLAND T.L.
The project extends from the Rutland town line to Brigham Road, a distance of 3.4 miles. The project involves resurfacing, drainage improvements, granite curbing, and sidewalk reconstruction. The existing cross-section varies between 37 and 41 feet.
Location:
  • Town of Hubbardston
  • Construction Begins: Winter 2017/2018
    Resident Engineer: Stephen Romano
    Construction Bid Price: $2,688,590.75
    District: District 3

    Contracts (1) Progress
    # 100229 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 68 (Worcester Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/13/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/21/2011
    Project Initiation Form PIF Entered 03/21/2011
    Project Initiation Form PRC Submitted 04/25/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/25/2011
    Project Status Advertised 04/22/2017
    Project Management
    100% Design 100% Package Received 08/18/2016
    100% Design 100% Package Comments to DE 09/23/2016
    100% Design 100% Plans Approved 09/23/2016
    25% Design 25% Package Received 01/06/2015
    75% Design 75% Package Received 01/06/2015
    75% Design 75% Package Comments to DE 02/18/2015
    75% Design 75% Package Comments to DE 02/19/2015
    75% Design 75% Package Comments to DE 04/23/2015
    Final Design PS&E Received 03/22/2017
    Final Design PS&E to FAPRO 04/10/2017