Project Description:
CHARLTON- BRIDGE SUPERSTRUCTURE REPAIRS AND RELATED WORK (INCLUDING PAINTING), C-06-03, (STEEL) STAFFORD STREET OVER I-90
Rpepair and replacement of a bridge girder damaged by vechicle hit. Partial deck and bridge rail replacement.
Location:
  • Town of Charlton
  • Resident Engineer: David Windoloski
    Construction Bid Price: $1,884,550.00
    District: District 3

    Contracts (4) Progress
    # 55042 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 69759 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77848 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 86884 -- Construction Contract
    Bridge Superstructure Repairs and Related Work (Including Painting) Br. No. C-06-038 (Steel) Stafford Street over Interstate 90 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/02/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/24/2011
    Project Initiation Form PIF Entered 04/13/2011
    Project Initiation Form PRC Submitted 04/13/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 03/07/2015
    Project Management
    100% Design 100% Package Received 05/08/2012
    25% Design 25% Package Received 07/21/2011
    25% Design 25% Package Comments to DE 07/21/2011
    75% Design 75% Package Received 03/07/2012
    Final Design PS&E Received 06/28/2013
    Final Design PS&E Received 06/09/2015
    Final Design PS&E to FAPRO 01/27/2014