PRINCETON- RECONSTRUCTION OF ROUTE 140, FROM STERLING T.L. THROUGH EAST PRINCETON VILLAGE TO ROUTE 31, INCLUDING REHAB OF P-16-017
The project involves roadway reclamation, drainage improvements, reconstruction of existing sidewalk and construction of new sections of sidewalk, and intersection improvements at Route 140 and Route 31. The project may also involve replacement of the Route 140 bridge over Keyes Brook.
Location:
  • Town of Princeton
  • Construction Begins: Autumn 2018
    Resident Engineer: Hassan Valipour
    Construction Bid Price: $6,561,398.90
    District: District 3

    Contracts (1) Progress
    # 105144 -- Construction Contract
    Roadway Reconstruction, Stone Wall Repairs and Bridge Superstructure Replacement Br. No. P-16-017 (Concrete) along a Section of Route 140 (Redemption Rock Trail) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/29/2018
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/24/2011
    Project Initiation Form PIF Entered 03/24/2011
    Project Initiation Form PRC Submitted 08/08/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Status Advertised 07/21/2018
    Project Management
    100% Design 100% Package Received 08/09/2017
    25% Design 25% Package Received 10/21/2013
    25% Design 25% Package Comments to DE 02/04/2015
    25% Design Design Public Hearing 04/28/2016
    75% Design 75% Package Received 12/21/2016
    Final Design PS&E Received 04/05/2018
    Final Design PS&E to FAPRO 07/09/2018