Project Description:
BUCKLAND- BRIDGE REPLACEMENT, B-28-002, ROUTE 112 (ASHFIELD ROAD) OVER CLARKS BROOK
(Replaces original #603280) The existing structure will be replaced in two stages with a bridge of the same width. Traffic will be maintained by alternating one lane traffic. A new sidewalk on the north side will be provided. Minimal approach roadway work will be performed so that the roadway width matches the bridge width. Additional improvements include new pavement markings and new signage.
Location:
  • Town of Buckland
  • Resident Engineer: Shannon Wilkins
    Construction Contract Value: $1,654,306.00
    Construction Bid Price: $1,494,669.50
    Initial Construction Estimate: $1,899,385.73
    District: District 1

    Contracts (3) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 58594 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 74045 -- Construction Contract
    Bridge Replacement (B-28-002) ('NEXT" Beam Concrete) - Ashfield Road (Route 112) over Clark Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/24/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/04/2011
    Project Initiation Form PIF Entered 04/04/2011
    Project Initiation Form PRC Submitted 04/04/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/26/2011
    Project Status Advertised 06/23/2012
    Project Management
    100% Design 100% Package Received 02/22/2012
    100% Design 100% Package Comments to DE 03/28/2012
    25% Design 25% Package Received 04/06/2011
    25% Design 25% Package Comments to DE 08/19/2011
    25% Design Design Public Hearing 09/28/2011
    75% Design 75% Package Received 11/15/2011
    75% Design 75% Package Comments to DE 02/06/2012
    Final Design PS&E Received 06/11/2012
    Final Design PS&E to FAPRO 06/20/2012