Project Description: |
BUCKLAND- BRIDGE REPLACEMENT, B-28-002, ROUTE 112 (ASHFIELD ROAD) OVER CLARKS BROOK
(Replaces original #603280) The existing structure will be replaced in two stages with a bridge of the same width. Traffic will be maintained by alternating one lane traffic. A new sidewalk on the north side will be provided. Minimal approach roadway work will be performed so that the roadway width matches the bridge width. Additional improvements include new pavement markings and new signage.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Albert Miller![]() |
Estimated Total Contract Cost: | $1,654,306.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 1 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|