Project Description:
GILL- GREENFIELD- BRIDGE REPLACEMENT, G-04-003=G-12-004, ROUTE 2 OVER THE FALL RIVER
(Replaces original #603504). The proposed project consists of rehabilitating the existing Route 2 bridge over Falls River in its present location with minor improvements to the approach roadways. The bridge will be replaced in stages and will remain open to vehicular and pedestrian traffic during construction.
Location:
  • Town of Gill
  • Town of Greenfield
  • Resident Engineer: -- not assigned --
    Construction Contract Value: $7,691,039.00
    Construction Bid Price: $6,962,763.00
    Initial Construction Estimate: $7,284,091.50
    District: District 2

    Contracts (3) Progress
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64320 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71101 -- Construction Contract
    Bridge Replacement (G-04-003=G-12-004) (Steel) - Route 2 over the Fall River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/19/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/06/2011
    Project Initiation Form PIF Entered 04/06/2011
    Project Initiation Form PRC Submitted 04/06/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Status Advertised 09/17/2011
    Project Management
    100% Design 100% Package Received 04/29/2011
    100% Design 100% Package Comments to DE 06/06/2011
    25% Design 25% Package Received 03/10/2009
    25% Design 25% Package Comments to DE 02/23/2011
    25% Design 25% Package Approved 04/14/2009
    25% Design Design Public Hearing 04/30/2009
    75% Design 75% Package Received 06/26/2009
    75% Design 75% Plans Approved 07/28/2009
    Final Design PS&E Received 09/06/2011
    Final Design PS&E to FAPRO 09/13/2011