Project Description:
CAMBRIDGE- BRIDGE REPLACEMENT, C-01-008, FIRST STREET AND C-01-040, LAND BOULEVARD OVER BROAD CANAL
Project involves the bridge substructure repair, superstructure repairs and painting of the following bridges: First Street Bridge C-01-008(4DM) and Land Blvd/Broad Canal C-01-040(4DL).
Location:
  • City of Cambridge
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Christopher I Cameron
    Estimated Total Contract Cost: $33,770,500.00
    Estimated Total Federal Participating Construction Cost: $35,858,355.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 09/14/2022 )

    Contracts (1) Progress
    # 59587 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CAMBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $11,065,600.00
    State Cost: $2,766,400.00
    Total Cost: $13,832,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/20/2011
    Project Initiation Form PIF Entered 04/20/2011
    Project Initiation Form PRC Submitted 04/20/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/27/2011
    Project Management
    Consultant Contract Process NTP Issued 09/14/2022
    Consultant Contract Process Workhours Approved 06/28/2011