Project Description: |
CAMBRIDGE- BRIDGE REPLACEMENT, C-01-008, FIRST STREET AND C-01-040, LAND BOULEVARD OVER BROAD CANAL
Project involves the bridge substructure repair, superstructure repairs and painting of the following bridges: First Street Bridge C-01-008(4DM) and Land Blvd/Broad Canal C-01-040(4DL).
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Autumn 2026 |
Project Manager: | Christopher I Cameron |
Estimated Total Contract Cost: | $33,770,500.00 |
Estimated Total Federal Participating Construction Cost: | $35,858,355.00 |
Funding Provision: | This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization. |
District: | District 6 |
Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 09/14/2022 ) |
|