Project Description:
HOLYOKE- TRAFFIC SIGNAL UPGRADES AND RELATED WORK ALONG HIGH AND MAPLE STREETS, FROM SOUTH STREET TO LYMAN STREET
Project will consist of replacing obsolete signal controllers with new controllers capable of incorporating progression and signal pre-emption systems (emergency as well as transit signal priority (TSP). Included will be tree trimming to improve sight distance and new signal heads, pedestrian signals, signage, wheel chair ramps and pavement markings.
Location:
  • City of Holyoke
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2022/2023
    Project Manager: Shahpar Negah
    Estimated Total Contract Cost: $9,178,856.88
    Estimated Total Federal Participating Construction Cost: $9,787,378.44
    Funding Provision: This project is planned to be funded through the 2022 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: Design Public Hearing (as of 08/18/2021 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2022
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: HOLYOKE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • STBG revised from $4,948,087.00 to $4,603,777 via STIP Action 6.
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $3,683,021.60
    State Cost: $920,755.40
    Total Cost: $4,603,777.00

    Planned Federal FY: 2022
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: HOLYOKE
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

  • HSIP revised from 5,425,894.00 to $6,151,624 via STIP Action 6.
  • Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $4,883,304.60
    State Cost: $542,589.40
    Total Cost: $5,425,894.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/21/2011
    Project Initiation Form PIF Entered 04/21/2011
    Project Initiation Form PRC Submitted 04/22/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/25/2011
    Project Management
    25% Design 25% Package Received 05/09/2016
    25% Design 25% Package Received 02/25/2019
    25% Design 25% Package Comments to DE 11/08/2016
    25% Design 25% Package Rejected 07/19/2017
    25% Design 25% Package Received - Resub 1 03/04/2020
    25% Design 25% Package Received - Resub 2 03/18/2021
    25% Design Design Public Hearing 08/18/2021