LENOX- RECONSTRUCTION & MINOR WIDENING ON WALKER STREET
This project will reconstruct and widen 1.55 miles of municipally owned roadway, including sidewalk reconstruction. The existing roadway (width varies 24-28 feet) will be widened to a uniform 30 feet (11 ft lanes with 4 ft shoulders). A project-length ADA compliant sidewalk will be achieved by reconstructing existing sidewalks and constructing new sidewalk where none currently exists. Drainage repairs/upgrades will target improving sub-grade and surface water runoff. The culvert over Woods Crossing Brook will be replaced. New traffic signs and markings will also be included.
Location:
  • Town of Lenox
  • Construction Begins: Spring 2019
    Resident Engineer: Michael Wall
    Construction Bid Price: $6,908,400.02
    District: District 1

    Contracts (1) Progress
    # 105923 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Walker Street (Route 183) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/13/2019
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/27/2011
    Project Initiation Form PIF Entered 05/05/2011
    Project Initiation Form PRC Submitted 05/05/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/25/2011
    Project Status Advertised 09/15/2018
    Project Management
    100% Design 100% Package Received 11/28/2017
    100% Design 100% Package Comments to DE 02/09/2018
    25% Design 25% Package Received 06/19/2012
    25% Design 25% Package Comments to DE 08/25/2012
    25% Design 25% Package Approved 10/01/2013
    25% Design Design Public Hearing 09/25/2013
    25% Design Design Public Hearing 10/24/2013
    75% Design 75% Package Received 01/04/2017
    75% Design 75% Package Comments to DE 02/22/2017
    Final Design PS&E Received 06/27/2018
    Final Design PS&E to FAPRO 08/31/2018