Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BUCKLAND- RECONSTRUCTION & MINOR WIDENING ON CONWAY STREET, SUMMER STREET, SOUTH STREET & CONWAY ROAD
This project will reconstruct and widen 1.7 miles of municipally owned roadway, including 1100 feet of sidewalk reconstruction to achieve ADA compliance. Project will also include reset/replacement of roadside curbing where required. Drainage repairs/upgrades will target improving sub-grade and surface water runoff. Guardrail runs and end-treatments on Conway Road will be upgraded to current safety standards. New traffic signs and markings will also be included.
Location:
  • Town of Buckland
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Darin Aitken
    Construction Bid Price: $7,946,772.50
    District: District 1

    Contracts (1) Progress
    # 116164 -- Construction Contract
    Roadway Reconstruction and Related Work on Sections of Conway, South and Summer Streets and Conway Road Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/12/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/27/2011
    Project Initiation Form PIF Entered 05/04/2011
    Project Initiation Form PRC Submitted 05/04/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/25/2011
    Project Status Advertised 08/28/2021
    Project Management
    100% Design 100% Package Received 04/19/2021
    100% Design 100% Package Comments to DE 05/25/2021
    25% Design 25% Package Received 05/15/2018
    25% Design 25% Package Received - Resub 1 09/21/2018
    75% Design 75% Package Received 09/14/2020
    75% Design 75% Package Comments to DE 11/17/2020
    Final Design PS&E Received 07/14/2021
    Final Design PS&E to FAPRO 08/16/2021
    Final Design PS&E Received - Resub 1 08/19/2021