Project Description:
DISTRICT 4- STRUCTURAL REPAIRS AT VARIOUS LOCATIONS
This project is to address the repairs to various bridge elements in District 4 that have been identified in inspection reports, concentrating first on safety issues. The current contract funds are being rapidly used for enormous repairs and are not enough to address all deficiencies that are identified in the inspection reports.
Location:
Resident Engineer: Thomas Zizza
Construction Contract Value: $2,938,426.27
Construction Bid Price: $337,947.97
Initial Construction Estimate: $472,445.00
District: District 4

Contracts (1) Progress
# 73150 -- Construction Contract
Scheduled and Emergency Bridge Structural Repairs at Various Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/13/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/04/2011
    Project Initiation Form PIF Entered 05/04/2011
    Project Initiation Form PRC Submitted 05/04/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/26/2011
    Project Status Advertised 03/31/2012
    Project Management
    Final Design PS&E Received 01/25/2012
    Final Design PS&E to FAPRO 03/27/2012