Project Description:
CHICOPEE- PALMER- WEST SPRINGFIELD- WESTFIELD- RAMP RESURFACING & RELATED WORK @ INTERCHANGES 3, 4 AND 5 ON I-90 (MM 40.4, 45.7 AND 49.0) AND MAINLINE MM 61.4 - 65.6
Work under this project will consist of milling and resurfacing ramps at I-90 interchanges 3 through 5 and the minaline from MM 61.4 to 65.6. Related work will include and drainage structure repairs, resetting granite edging, new curb/berm as required and new pavement markings.
Location:
  • City of Chicopee
  • Town of Palmer
  • Town of West Springfield
  • City of Westfield
  • Resident Engineer: Joseph Borowiec
    Construction Contract Value: $2,932,079.00
    Construction Bid Price: $2,439,286.50
    Initial Construction Estimate: $2,524,906.00
    District: District 2

    Contracts (1) Progress
    # 72312 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 90 and on Ramps at Interchanges 3, 4 and 5. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/29/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/05/2011
    Project Initiation Form PIF Entered 05/05/2011
    Project Initiation Form PRC Submitted 05/06/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/25/2011
    Project Status Advertised 12/31/2011
    Project Management
    25% Design 25% Package Received 11/22/2011
    75% Design 75% Package Received 11/22/2011
    75% Design 75% Package Comments to DE 12/02/2011
    Final Design PS&E Received 12/16/2011
    Final Design PS&E to FAPRO 12/27/2011