Project Description:
SOUTH HADLEY- RESURFACING & RELATED WORK ON ROUTE 202, FROM DOUGLAS STREET TO ROUTE 33
(Replaced #606009) This project involves resurfacing and related work on a section of Route 202 in South Hadley. The project begins at the intersection with Douglas Street, Sta. 72+00, and proceeds northerly to the Route 33 intersection, Sta. 70+55, for a total project length of 4,497 feet (0.85 miles). The work will consist of milling the existing pavement and resurfacing with hot mix asphalt; removing and resetting sections of granite curb and edging; replacing hot asphalt curb; adjusting and rebuilding existing drainage structures; cleaning drainage structures and pipes; new pavement markings and slotted pavement markers; constructing new wheelchair ramps, reconstructing driveways and sidewalks; tree trimming; erosion & sedimentation control; and other incidental items as necessary.
Location:
  • Town of South Hadley
  • Resident Engineer: Jonathan Giraldo
    Construction Contract Value: $885,364.00
    Construction Bid Price: $771,219.25
    Initial Construction Estimate: $764,696.00
    District: District 2

    Contracts (1) Progress
    # 72266 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 202 (Granby Road). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/25/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/11/2011
    Project Initiation Form PIF Entered 05/11/2011
    Project Initiation Form PRC Submitted 05/11/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/27/2011
    Project Status Advertised 12/24/2011
    Project Management
    Final Design PS&E Received 12/15/2011
    Final Design PS&E to FAPRO 12/19/2011