Project Description:
BOSTON- ROADWAY, CEILING, ARCH & WALL RECONSTRUCTION AND OTHER CONTROL SYSTEMS IN SUMNER TUNNEL
Project involves the reconstruction of the roadway within Summer Tunnel and the repair of exhaust plenum and ceiling.
Location:
  • City of Boston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2021
    Project Manager: Steven E McLaughlin
    Estimated Total Contract Cost: $130,296,500.00
    Estimated Total Federal Participating Construction Cost: $136,190,450.00
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 06/26/2021 )

    Contracts (8) Progress
    # 102481 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide road and bridge projects, for the purpose of mainta Final
    # 60493 -- Non-system contract type
    Statewide - Owner's Representative will perform peer reviews and manage cost recovery and value engineering for various projects
    # 69761 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various highway and bridge projects. Final
    # 77867 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77868 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77870 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77878 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77879 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/12/2011
    Project Initiation Form PIF Entered 05/12/2011
    Project Initiation Form PRC Submitted 05/13/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/26/2011
    Project Status Advertised 06/26/2021
    Project Management
    100% Design 100% Package Received 04/20/2016
    25% Design 25% Package Received 05/28/2015
    25% Design 25% Package Comments to DE 09/22/2015
    75% Design 75% Package Received 10/14/2015
    75% Design 75% Package Comments to DE 12/07/2015
    Final Design PS&E Received 05/28/2021
    Final Design PS&E to FAPRO 06/14/2021