Project Description:
CALLAHAN TUNNEL VENT BUILDING 13 BRICK FACADE RENOVATION AND REPAIRS AT LONDON AND DECATUR STREETS
Project involves the replacement of the Callahan Tunnel vent building wall located in East Boston.
Location:
  • City of Boston
  • Construction Begins: Summer 2015
    Resident Engineer: Pasquale Mele
    Construction Contract Value: $10,012,850.00
    Construction Bid Price: $8,559,000.00
    Initial Construction Estimate: $7,747,000.00
    District: District 6

    Contracts (1) Progress
    # 85135 -- Construction Contract
    Callahan Tunnel Vent Building 13 Brick Facade Renovation and Repairs at London and Decatur Streets. DCAMM Category: GENERAL BUILDING CONSTRUCTION Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/10/2015
    Contract Information
    Project Designer: Consultant
    Funding Source: Metropolitan Highway System
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/13/2011
    Project Initiation Form PIF Entered 05/13/2011
    Project Initiation Form PRC Submitted 05/13/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/26/2011
    Project Status Advertised 09/27/2014
    Project Management
    100% Design 100% Package Received 07/16/2014
    Final Design PS&E Received 09/24/2014
    Final Design PS&E to FAPRO 09/24/2014