Project Description:
MILLBURY- SUTTON- MEDIAN BARRIER REPLACEMENT ON ROUTE 146, FROM ROUTE 122A TO BOSTON ROAD
The project entails replacing existing deteriorated concrete median barrier. Additional work will entail permanent closure of median breaks that were closed with temporary barrier and minor roadway repairs associated with the barrier installation and median closures.
Location:
  • Town of Millbury
  • Town of Sutton
  • Resident Engineer: Stephen Shamoian
    Construction Bid Price: $5,794,360.00
    District: District 3

    Contracts (2) Progress
    # 56818 -- Design -- Services
    Work will consist of providing statewide photogrammetric services on an as need, assignment basis over a period of 60 months. Final
    # 90406 -- Construction Contract
    Resurfacing, Median Barrier Replacement and Related Work along Sections of Route 146 (Worcester-Providence Turnpike). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/15/2016
    Contract Information
    Project Designer:
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/19/2011
    Project Initiation Form PIF Entered 05/19/2011
    Project Initiation Form PRC Submitted 05/19/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/27/2011
    Project Status Advertised 08/29/2015
    Project Management
    100% Design 100% Package Received 01/16/2015
    100% Design 100% Package Comments to DE 03/04/2015
    25% Design 25% Package Received 04/15/2014
    25% Design 25% Package Comments to DE 07/03/2014
    25% Design 25% Package Approved 04/15/2014
    25% Design 25% Plans Complete 04/15/2014
    75% Design 75% Package Received 04/15/2014
    75% Design 75% Package Comments to DE 07/03/2014
    75% Design 75% Plans Approved 04/15/2014
    75% Design 75% Plans Complete 04/15/2014
    Final Design PS&E Received 08/20/2015
    Final Design PS&E to FAPRO 08/26/2015