WARREN- WEST BROOKFIELD- RESURFACING & RELATED WORK ON ROUTE 67, FROM THE PALMER/WARREN T.L. TO ROUTE 9 (APPROX 4.85 MILES)
The project will mill and overlay the state-maintained sections of Route 67 in Warren and West Brookfield from the Palmer/Warren Town Line to Route 9 in West Brookfield. Two areas from MM 6.10 to MM 6.46 and from MM 8.44 to MM 9.02 will not be included in the project. The total project distance is 4.85 miles. It will include new pavement markings and recessed pavement markers. There are some bridges and culverts within the limits of the project that will be resurfaced. Wheelchair ramps in the paving area will be updated to current standards.
Location:
  • Town of Warren
  • Town of West Brookfield
  • Resident Engineer: Mark Shea
    Construction Contract Value: $1,953,449.00
    Construction Bid Price: $1,694,765.50
    Initial Construction Estimate: $1,833,308.00
    District: District 2

    Contracts (1) Progress
    # 72267 -- Construction Contract
    Resurfacing and Related Work on Sections of Route 67. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/14/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/23/2011
    Project Initiation Form PIF Entered 05/23/2011
    Project Initiation Form PRC Submitted 05/24/2011
    Project Review Committee PRC Approved 05/19/2011
    Project Review Committee Letter 05/26/2011
    Project Status Advertised 12/24/2011
    Project Management
    75% Design 75% Package Received 06/14/2011
    Final Design PS&E Received 12/09/2011