| Project Description: |
NORTHBRIDGE- RECONSTRUCTION OF SUTTON STREET, FROM SUTTON T.L. TO ROUTE 122 (APPROX. 2.2 MILES)
(Replaced #601371). The proposed project consists of full depth roadway reconstruction on Sutton Street between the Northbridge town line and the intersection of Route 122/Providence Road. Work includes minor roadway widening, pavement overlay, new drainage, and reconstructed/extended sidewalks.
|
| Location: |
|
| Resident Engineer: | Hassan Valipour![]() |
| Construction Contract Value: | $7,042,190.60 |
| Construction Bid Price: | $7,003,961.92 |
| Initial Construction Estimate: | $7,430,407.00 |
| District: | District 3 |
|
Bridges |
||||||||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||