Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HOLBROOK- RECONSTRUCTION OF UNION STREET (ROUTE 139), FROM LINFIELD STREET TO CENTRE STREET/WATER STREET
The purpose of this project is to rehabilitate a segment of Union Street from Linfield Street to Centre Street/Water Street. The proposed improvements will address poor roadway pavement conditions, deteriorating sidewalks, a lack of curbing and needed drainage improvements. The project will also address the need for upgraded pavement markings, signage and guard rail.
Location:
  • Town of Holbrook
  • Construction Begins: Winter 2020/2021
    Resident Engineer: Russell Davis
    Construction Bid Price: $3,131,034.16
    District: District 5

    Contracts (1) Progress
    # 113397 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Union Street (Route 139) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/11/2021
    Contract Information
    Project Designer: Municipality
    Funding Source: TAP
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/27/2011
    Project Initiation Form PIF Entered 11/01/2011
    Project Initiation Form PRC Submitted 11/02/2011
    Project Review Committee PRC Approved 11/17/2011
    Project Status Advertised 10/31/2020
    Project Management
    100% Design 100% Package Received 07/30/2019
    100% Design 100% Package Comments to DE 11/01/2019
    25% Design 25% Package Received 05/24/2013
    25% Design 25% Package Comments to DE 03/06/2014
    25% Design Design Public Hearing 04/06/2016
    75% Design 75% Package Received 04/26/2018
    75% Design 75% Package Comments to DE 10/15/2018
    Final Design PS&E Received 04/17/2020
    Final Design PS&E Received - Resub 1 09/21/2020