Project Description:
NEWBURY- NEWBURYPORT- CLIPPER CITY RAIL TRAIL ALONG THE CITY BRANCH (PHASE II)
The project will construct a multi-use trail along the City Branch former rail. The path will begin at the existing board walk near the Custom House Maritime Museum in Downtown Newburyport following the Merrimack River then turning inland across Water Street between Bromfield Street and Harrison Street and continue along the rail bed to Route 1A (High Street). The length will be approximately 1.1 miles. An option of extending this section of the path to Parker Street is being considered. This section would add approximately 1/2 mile to the path.
Location:
  • Town of Newbury
  • City of Newburyport
  • Resident Engineer: Kenneth Wong
    Construction Bid Price: $4,845,342.00
    District: District 4

    Contracts (2) Progress
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final
    # 90715 -- Construction Contract
    Construction of the Clipper City Rail Trail (Phase II). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/01/2016
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/01/2011
    Project Initiation Form PIF Received 07/01/2011
    Project Initiation Form PIF Entered 07/01/2011
    Project Initiation Form PRC Submitted 07/12/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Status Advertised 09/19/2015
    Project Management
    100% Design 100% Package Received 06/18/2015
    100% Design 100% Package Comments to DE 07/23/2015
    25% Design 25% Package Received 07/02/2013
    25% Design 25% Package Comments to DE 01/17/2014
    25% Design Design Public Hearing 03/26/2014
    75% Design 75% Package Received 11/04/2014
    75% Design 75% Package Comments to DE 02/24/2015
    Final Design PS&E Received 09/10/2015
    Final Design PS&E to FAPRO 09/16/2015