Project Description:
SOMERVILLE- MEDFORD- GREEN LINE EXTENSION INCLUDING WORK ON 5 BRIDGES: S-17-007 (MEDFORD ST), S-17-008 (SCHOOL ST), S-17-011 (LOWELL ST), S-17-013 (BROADWAY), AND MEDFORD M-12-012 (COLLEGE AVE)
As part of the Greenline Extension Project, MBTA is replacing Medford Street, Lowell Street, Broadway, College Ave and School Street over the MBTA rail corridor.
Location:
  • City of Medford
  • City of Somerville
  • Design Responsibility: Other
    Project Manager: Matt Hopkinson
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: 75% Package Received (as of 02/24/2014 )

    Contracts (5) Progress
    # 115745 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 65757 -- Design -- Geotechnical
    Work will consist of Geotechnical Review during the design of bridge structures and/or roadways owned by MassDOT and Cities and Towns throughout the Commonwealth. Final
    # 66702 -- Design -- Geotechnical
    Work will consist of Geotechnical design and review services for roadway and bridge projects statewide. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/05/2011
    Project Management
    25% Design 25% Package Received 04/17/2012
    25% Design 25% Package Comments to DE 02/17/2012
    75% Design 75% Package Received 02/24/2014