Project Description:
CHARLEMONT- CULVERT REPLACEMENT, C-05-025, ROUTE 2 OVER HARTWELL BROOK
This project proposes to replace a deteriorating concrete culvert with a new single-span bridge. To satisfy current Massachusetts Stream Crossing Standards, the proposed bridge span will need to be approximately 30 feet (i.e. 3 times wider than the existing 10 foot span) with a curb-to-curb deck width of 32 feet. The proposed design will strive for rural context sensitivity. Under current consideration is the use of a pre-cast concrete three-sided culvert; to allow design of a scour-resistant, natural stream bed bottom. A gabion wall on the east side of the upstream channel will also be repaired. No sidewalks exist at this location, and none are currently proposed. Expedited construction techniques will be considered, and work in the water will be reduced to the extent possible. Signalized, alternating one-way traffic on Route 2 will be maintained during construction.
Location:
  • Town of Charlemont
  • Resident Engineer: Timothy Moore
    Construction Contract Value: $1,423,669.12
    Construction Bid Price: $1,223,988.30
    Initial Construction Estimate: $1,435,339.10
    District: District 1

    Contracts (2) Progress
    # 64302 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 75232 -- Construction Contract
    Route 2 Culvert Replacement (C-05-025) (Concrete) over Hartwell Brook. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/21/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/08/2011
    Project Initiation Form PIF Entered 07/08/2011
    Project Initiation Form PRC Submitted 08/02/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 08/25/2012
    Project Management
    100% Design 100% Package Received 03/23/2012
    100% Design 100% Package Comments to DE 05/22/2012
    25% Design 25% Package Received 11/28/2011
    25% Design 25% Package Comments to DE 02/27/2012
    25% Design Design Public Hearing 01/24/2012
    75% Design 75% Package Received 03/23/2012
    Final Design PS&E Received 08/10/2012
    Final Design PS&E to FAPRO 08/20/2012