| Project Description: |
DISTRICT 5- UNDERGROUND STORAGE TANK REMOVAL & REPLACEMENT AT THE HANOVER DEPOT
This project is to replace existing steel underground fuel storage tanks that have developed a leak in the outer containment wall. The proposed tanks are fiber glass that are not susceptable to corrosion.
|
| Location: | |
| Resident Engineer: | Jeffrey Peterson![]() |
| Construction Contract Value: | $271,032.00 |
| Construction Bid Price: | $235,680.00 |
| Initial Construction Estimate: | $221,330.00 |
| District: | District 5 |
|
Bridges |
||||||||
|
||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||