Project Description:
BLANDFORD- CULVERT REPLACEMENT, B-14-029, I-90 OVER UNNAMED TRIBUTARY TO PEEBLES BROOK
This project proposes to replace an existing 84 inch corrugated metal culvert that has failed under I-90 at MM 25.6. The culvert is approximately 330 feet long and conveys flow from north to south under the westbound and eastbound lanes of the highway. The proposed culvert will be installed adjacent to the existing culvert using tunneling techniques. The existing culvert will be filled and abandoned in place.
Location:
  • Town of Blandford
  • Resident Engineer: Erin Cooper
    Construction Contract Value: $5,446,838.00
    Construction Bid Price: $4,699,424.50
    Initial Construction Estimate: $4,833,640.00
    District: District 1

    Contracts (6) Progress
    # 55038 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57732 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects, includes ABP projects Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 79504 -- Construction Contract
    Bridge Culvert Replacement (B-14-029) (Jacked Concrete Pipe) - Interstate 90 over Unamed Tributary to Peebles Brook. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/06/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Western Turnpike
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/18/2011
    Project Initiation Form PIF Entered 07/18/2011
    Project Initiation Form PRC Submitted 08/02/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 08/31/2013
    Project Management
    25% Design 25% Package Received 09/14/2012
    25% Design 25% Package Comments to DE 10/09/2012
    25% Design 25% Package Approved 11/13/2012
    75% Design 75% Package Received 01/23/2013
    75% Design 75% Package Comments to DE 02/25/2013
    Final Design PS&E Received 08/16/2013
    Final Design PS&E to FAPRO 08/26/2013
    Consultant Contract Process Scope to DE 05/16/2012
    Consultant Contract Process NTP Issued 06/15/2012
    Consultant Contract Process Workhours Approved 05/30/2012