Project Description:
WAKEFIELD- SAFE ROUTES TO SCHOOLS (DOLBEARE SCHOOL)
The proposed improvements include the construction of sidewalks in the following locations surrounding the Dolbeare School: east side of Vernon Street between Lowell Street and Sesame Street, west side of Vernon Street between Lowell Street and school driveway, north side of Lowell Street between Vernon Street and westerly school driveway. The project also includes installation of a pedestrian flasher assembly on Lowell Street in front of the school, installation of pedestrian countdown signals at the Lowell Street / Vernon Street intersection, reconstruction of the Shell gas station driveways to reduce the length of pedestrian crossings, instillation of bike racks and better define curb cuts, and construction of sidewalk connections between Lowell Street and Vernon Street and the school entrances.
Location:
  • Town of Wakefield
  • Resident Engineer: Fred Collins
    Construction Contract Value: $442,063.00
    Construction Bid Price: $378,739.34
    Initial Construction Estimate: $405,235.00
    District: District 4

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 78358 -- Construction Contract
    Sidewalk Improvements on Sections of Lowell and Vernon Streets (Safe Routes to School - Dolbeare Elementary School) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/01/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/19/2011
    Project Initiation Form PIF Entered 07/19/2011
    Project Initiation Form PRC Submitted 07/21/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 07/13/2013
    Project Management
    100% Design 100% Package Received 02/04/2013
    100% Design 100% Package Comments to DE 03/26/2013
    25% Design Design Public Hearing 12/13/2012
    75% Design 75% Package Received 07/12/2012
    75% Design 75% Package Comments to DE 09/17/2012
    Final Design PS&E Received 04/17/2013
    Final Design PS&E to FAPRO 07/08/2013