Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
QUINCY- CONSTRUCTION OF NEW CONNECTION (BRIDGE) FROM BURGIN PARKWAY OVER MBTA
As part of the Quincy Redevelopment project, the city plans to construct a new bridge over the existing MBTA tracks that will connect the downtown area at Market Square and Hancock Street. The main goal of the new bridge will be improved pedestrian conditions along Hancock Street.
Location:
  • City of Quincy
  • Construction Begins: Autumn 2018
    Resident Engineer: Robert Fink
    Construction Bid Price: $9,156,557.00
    District: District 6

    Contracts (3) Progress
    # 104746 -- Construction Contract
    Bridge Construction Br. No. Q-01-031 Burgin Parkway Access Road over MBTA Red Line (Pre-Fabricated Bridge Units) Completed
    # 115778 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77874 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/13/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/19/2011
    Project Initiation Form PIF Entered 07/19/2011
    Project Initiation Form PRC Submitted 07/19/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 07/07/2018
    Project Management
    100% Design 100% Package Received 02/23/2018
    25% Design 25% Package Received 12/16/2016
    25% Design 25% Package Comments to DE 12/20/2016
    25% Design Design Public Hearing 05/02/2017
    75% Design 75% Package Received 09/21/2017
    Final Design PS&E Received 06/08/2018
    Final Design PS&E to FAPRO 06/20/2018