Project Description:
BROCKTON- SAFE ROUTES TO SCHOOL (BROOKFIELD ELEMENTARY SCHOOL)
Work consists of constructing sidewalks and other related work at the Brookfield Elementary School.
Location:
  • City of Brockton
  • Resident Engineer: Christopher Sera
    Construction Contract Value: $503,474.00
    Construction Bid Price: $447,704.00
    Initial Construction Estimate: $470,088.00
    District: District 5

    Contracts (2) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 77811 -- Construction Contract
    Sidewalk Improvements on Sully Road and Sections of Jon Drive (Safe Routes to School - Brookfield Elementary School). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/20/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Safe Routes to Schools
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/19/2011
    Project Initiation Form PIF Entered 07/22/2011
    Project Initiation Form PRC Submitted 07/22/2011
    Project Review Committee PRC Approved 08/11/2011
    Project Review Committee Letter 08/19/2011
    Project Status Advertised 06/08/2013
    Project Management
    100% Design 100% Package Received 11/15/2012
    100% Design 100% Package Comments to DE 02/13/2013
    25% Design 25% Package Received 04/24/2012
    25% Design Design Public Hearing 10/17/2012
    Final Design PS&E Received 03/20/2013
    Final Design PS&E to FAPRO 06/05/2013